Project Avantika Nehru Place

Avantika Nehru Place

The client asked our founder, Mr. Venkat, when the Nehru Place store could start operations. Sir responded that we could only plan operations once the work had started. The client then asked if it was possible to start within two days. Mr. Venkat responded confidently—we would try to do it in four. Within the next six hours, all planning was completed, and the team moved to the site. That’s when we received unexpected news—work was allowed only at night. Instead of slowing down, we reorganized the entire execution plan: on-site work continued at night, while all fabrication and preparation were carried out during the day off-site. In record time, we completed firefighting systems, electrical works, ducting, air-conditioning, wall finishes, glass doors, smoke detectors, racks, and counters. What followed became a remarkable milestone in our journey—one that proudly stands in our record book.

Interior

Project Type:
Liquor Retail
Clients:
SRI AVANTIKA CONTRACTOR LTD.
Location:
NEHRU PLACE, NEW DELHI
Main Image
Thumbnail 1 Thumbnail 2 Thumbnail 3 Thumbnail 4 Thumbnail 4 Thumbnail 4 Thumbnail 4 Thumbnail 4 Thumbnail 4

Frequently Asked Questions

Within just six hours of discussion, the entire execution plan was finalized, and the team moved to the site. The speed of planning played a key role in achieving this milestone.

When the client asked about starting operations within two days, Mr. Venkat confidently committed to trying within four days—setting the tone for a highly focused execution.

Our office address is: 10 LGF, Vinobapuri, Lajpat Nagar-Part 2, New Delhi – 110024. You can reach us by phone: +91 99900 36969 or via email: info@nextbc.in. While our base is in Delhi-NCR, we undertake projects Pan India.

You can contact us via:

  • The Contact Us form on our website: www.nextbc.in
  • Email: info@nextbc.in
  • Call/WhatsApp: +91 99900 36969

Once we connect, we will gather details (scope, size, vision, budget) and provide a tailored proposal.

After mobilization, we were informed that work was permitted only during night hours This required an immediate change in execution strategy.

The entire workflow was reorganized On-site work was carried out at night while fabrication preparation and coordination were handled during the day off-site to avoid any slowdown.